As you are aware we are going through several updates and renovations at our locations. We want to let you know in advance that we will begin having tile replacement done at our Huntley location. The project will start this week and will continue over the next month in phases.
Below is a breakdown of each location along with timelines for each phase of this project.
Men’s Shower: 1 side at a time
Phase 1: 10/31 – 11/27
Phase 2: 11/28 – 12/27
Men’s Steam Room
Phase 1: 11/21 – 12/4
Family Changing Room: 2 Rooms at a time
Phase 1: 11/8 – 11/21
Phase 2: 11/22 – 12/5
Phase 3: 12/6 – 12/19
Assisted Changing Room:
Phase 1: 11/21 – 12/4
Phase 2: 12/5 – 12/18